About COSEIMIQ

The project is organized in four work packages (WPs):

  • WP1 Demonstration Case;
  • WP2 Microseismic Monitoring and Imaging;
  • WP3 Geomechanical Modeling;
  • WP4 Risk Assessment and Mitigation.

Project Timeline

Project Timeline

List of deliverables

D1

Implementation of advanced micro-seismicity monitoring tools in SeisComp3 modules and workflows optimized for geothermal plays.

D2

Implementation of advanced imaging tools in workflows optimized for geothermal plays.

D3

Coupled geo-mechanical and reservoir modeling framework implemented within RISC, ready for real- time application and adopted to Icelandic conditions. Integration of the methods developed in the WP2, WP3 and WP4 in a single tool (the RISC tool).

D4

Risk and Safety assessment calibrated for Icelandic conditions and extended to allow the distinction between natural and induced seismicity.

D5

Offline calibration and performance evaluation of the RISC system

D6

Demonstration of the RISC decision support framework at the Hengill site in real time.

D7

RISC tool ready for other commercial applications in Europe.

List of milestones

M1

Collection of existing data and seismic network design and optimization

M2

Installation of the seismic network at the Hengill site.

M3

Integration of the methods developed in the WP2, WP3 and WP4 in a single tool (the RISC tool).

M4

Start of the testing phase of the RISC tool with real time data at the Hengill demonstration site.